NVR Logo
City, contractor have looming deadline for span near Copia
A view of the Napa River as construction takes place for the new First St. Bridge near Copia. City workers rus to complete the project by October 15, when construction in the waterway must end for the rain season. Lianne Milton/Register | Buy photos
Saturday, August 30, 2008
Save and Share Share
Construction of the new Napa River bridge at First Street is going at a furious pace to beat the winter rains.

Workers have been laboring 10 hours a day, six days a week and are prepared to add a seventh day if necessary, Jason Holley, the city of Napa engineer in charge of the project, said last week.
The general contractor, American Civil Constructors, is up against a tight deadline to finish work in the river by Oct. 15, a requirement of the Regional Water Quality Control Board, Holley said.

Demolition of the old concrete bridge, built in 1914, was wrapping up last week, leaving just six and a half weeks to build the piers and abutments for the new bridge, he said.
“It’s a very tight schedule. We’re confident we can get it done,” Holley said.

Workers are finishing the process of sinking sheet piles for cofferdams that will hold back the river, creating dry pockets for the construction of abutments and piers.
Over the next two to three weeks, workers will pound some 200 steel piles, each 85 feet long, into the river bed. The piles will be surrounded with concrete, becoming the foundation of the new span.

While sinking sheet piles for the cofferdams was loud, pounding foundation piles will be louder, Holley said. To speed up work, the contractor may bring in a second hammer so that two piles can be sunk at the same time, he said.

It’s essential that the foundation of the new bridge be completed by Oct. 15 so that construction of the deck can occur over the winter months, Holley said.

If for some reason the foundation is not completed by mid-October, work might not be able to resume in the river bed until next July.

Work is allowed in the waterway only between July 15 and Oct. 15 to protect fish that might be present during periods of elevated river flows, Holley said.

If Oct. 15 approaches and winter rains have held off, the city might be able to get a permit extension until Oct. 31, but this cannot be counted on, Holley said.

The new bridge will be higher and longer than the old one, eliminating a flood obstruction. The price tag for the project is $15.1 million, with the federal government paying 88.5 percent of most costs, Holley said. The city is paying the rest.

The reinforced concrete in the old bridge is being recycled for new construction projects, Holley said. The city saved the plaque on the old bridge for a future historical display, he said.

First Street isn’t scheduled to be reopened to traffic until July 2009. In the meantime, vehicles are being detoured to Lincoln Avenue and Third Street.

The construction is occurring adjacent to Copia, which remains fully open. The privacy of Copia’s gardens and outdoor dining at Julia’s Kitchen is partially protected by 10-foot fences that have been painted green.

Part of Copia’s north garden was wiped out by the construction of a temporary access road for deliveries. Copia salvaged a number of displaced olive trees, Holley said.
12 comment(s)

comment wrote on Aug 30, 2008 12:50 AM:

" I hate when they drive those foundation piles. It's so loud! I would not want to be working at Copia during that time. "

napamom21 wrote on Aug 30, 2008 8:39 AM:

" Forget working at Copia - try living next to this mess and hear it going on all the time! It's ridiculous and it doesn't help to have a slumlord that conveniently neglects to disclose the construction. "

musikluvr wrote on Aug 30, 2008 9:40 AM:

" This bridge work is going to destroy the new businesses on First Street next to Copia. They should be compensated by the city for this. "

wyngrrrl13 wrote on Aug 30, 2008 11:14 AM:

" Imagine being in one of the 3 houses that are opposite of the old J.V. site. Those are the people that we should have sympathy for, they have to LIVE with the construction of the bridge. Can you imagine what is going to happen to the foundation of those homes by using not one, but two hammers for the foundation piles? "

comment wrote on Aug 30, 2008 2:13 PM:

" If they're new businesses, they should have known this was going to happen. The bridge replacement has been planned for years. I don't mean it to sound cold, it would be unfortunate if they went out of business do to decreased traffic, but I don't think they deserve compensation. "

selim wrote on Aug 30, 2008 2:50 PM:

" Er, musikluvr, I was just in the Oxbow/Copia area and it didn't seem like the businesses there were hurting at all. In fact, the Oxbow was the most crowded I've ever seen...I imagine the surrounding businesses must be doing well, too. Bottom line: if you're within 2 blocks of the Oxbow and YOU go out of business, it can probably be chalked up to lack of business smarts, not much needed bridge construction. "

cordell wrote on Aug 30, 2008 4:43 PM:

" How dare they make all that noise building a new bridge that will help everyone. Any fool knows that they could have used MAGIC to set that foundation. "

npma wrote on Aug 30, 2008 8:41 PM:

" Thank you cordell,These guys are trying to help with flood control so stop all the negativity and get on with your day "

auntielmo wrote on Aug 30, 2008 8:50 PM:

" wyngrrrl13 ... Thank you for your comment. I live in 1 of those 3 house across from the old JV. It's pretty frustrating that I have to read about what will be happening here in the construction zone in the Napa Register. It would be nice if we would have been told by the CITY engineer Jason. The communication between the city & the 3 houses is totally unacceptable. I send emails & it either takes days to get a response or no response at all.

How would you like to live with a generator running 24/7 right next to your bedroom window. Or have major safety hazards from broken utility boxes and nothing being done about it. Even after sending the city an email.

We were told they will start construction on Saturday @ 9 am, yet at 6:45 am this morning we were awoken by construction noise. And just the night before they worked until almost 9 pm. And having equipment dropped off at 11:30 pm at night.

I have tried to have patience, but my patience has ran out. There is no respect for us what so ever. There has just been to many things that have happened to have patience anylonger.

So if any of the people who live in this area. We were informed this afternoon that they will be working on Monday Labor day from 7 am - 5:30 pm. So if anyone was planning on having a bbq, you may want to reconsider. I know we cancelled our plans. I emailed Jason on Wednesday asking if they were working & finally got a response on Saturday afternoon. Which is totally unacceptable!!!!!! "

auntielmo wrote on Aug 30, 2008 10:16 PM:

" wyngrrrl13 comment ... Can you imagine what is going to happen to the foundation of those homes by using not one, but two hammers for the foundation piles?

Let me just say. The pile driving hasnt even started yet, and our house has already shifted. Our shower door doesnt shut right anymore. Our neighbors bedroom door, she cant even close now.

So I can only image what is going to happen when they start pile driving. I guess we are going to have to take more stuff off the shelves & walls. Since we already lost stuff just from the vibration of them installing the cofferdams. "

dbass wrote on Aug 31, 2008 8:56 PM:

" I have lived in Napa for 18 years and support this bridge project. It will indeed improve the city of Napa and aid in the flood relief. My concern is also for the three houses that sit at the construction site and for the people who reside in them. My daughter lived in the house closest to the construction but due to noise, dirt, insects and lack of communication had to leave her house. She moved out yesterday and was sad to leave her neighbors, room mate and neighborhood. Because of the noise, unpredicatable work schedule, safety hazards, dirt and insects she had no choice but to leave her home. Unfortuntly for the other residence this is only the beginning of the construction. The city of Napa needs to be more considerate of these people. There is no escape from this construction when they continue to work 7 days a week with equipment running 24 hours a day. Everyone understands that there are deadlines to meet but even the workers who are there 7 days a week get to go home to a construction free zone. The residence on First St come home to the construction. "

msmith wrote on Sep 2, 2008 1:27 PM:

" I have been a homeowner on First Street (second house from the Napa River) since 2000 and have suffered loss & damage from flooding. I welcome and support the recent and upcoming changes to our neighborhood and city. I, along with my neighbors have attended years of planning meetings in support of this project. In no way do any of the 3 residences on the 400 block of First St., who are severely impacted by the day to day construction, oppose this project. All we have asked from the beginning is for the channels of communication between the city, contractors and ourselves, to remain open. We asked that if the schedule for construction was to go beyond the M-F 7-5 or even 7-7, that we be notified. This has not consistently happened. There have been been a few Sundays where the crew showed up to work a full day and we were never notified. Thus, two weekends in a row, impacting our personal plans/lives/schedules. Normally, this might not be such an issue, but when you have lost numerous hours of sleep due to 24hr loud generators, early morning construction (starting before 7 am) and come home from work to late construction (up to 9 pm) and even a late night delivery (11:30 PM) which wakes you from your sleep, patience begins to waiver. Not to mention, we have lost access to our driveways (where we normally park our vehicles) and forced to park around the corner where are vehicles are no longer visible from our homes. Even as I type this, my 100+ yr old home shakes and windows vibrate. I can no longer close one of my interior doors, noticed cracks where they did not exist prior to this project...I am worried about my home. "

Comment Guidelines
The goal of the story comments section at NapaValleyRegister.com is to have an open, thought-provoking, civil community forum for all issues.
What gets your comment posted?
• Staying on topic
• Keeping your comment to 300 words or less
• Avoiding name-calling
• Addressing your comments to the message rather than the messenger
What gets your comment deleted?
• Personal attacks
• Derogatory remarks
• Name-calling of any sort
• Going off-topic
• Hate speech
• Racially-insensitive comments
• Implying guilt of a subject in a crime story before there is a court verdict
• Posting e-mail addresses
• Posting comments of a commercial nature
• POSTING WITH ALL CAPITAL LETTERS
• Linking multiple comments together with "to be continued..." to get around the 300 word limit.
The fine print
- Comments are either approved or denied. We do not edit comments.
- You are welcome to modify and resubmit a denied comment.
- Comments may take several hours to be posted.
- Comments posted are those of the writer, and do not necessarily reflect the opinion of NapaValleyRegister.com, its employees or its parent company.
- Do you have information on a story? Please go to our virtual newsroom to send us a news tip.
- If you feel a posted comment has violated our guidelines, please contact online@napanews.com or add a comment indicating you have an issue and our moderators will review the comment in question.
Search:
Web Search Powered
By Yahoo! Search
Napa Valley Register on Facebook
Copyright © 2009 Napa Valley Publishing, a member of Lee Enterprises, Inc.
Terms of Use | Privacy Policy